The time estimates obtained from four contractors (P, Q, R and S) for executing a particular job are as under:
\[\begin{array}{|c|c|c|c|} \hline \textbf{Contractor} & \textbf{Optimistic time, $t_o$} & \textbf{Most likely time, $t_m$} & \textbf{Pessimistic time, $t_p$} \\ \hline \text{P} & 5 & 10 & 13 \\ \hline \text{Q} & 6 & 9 & 12 \\ \hline \text{R} & 5 & 10 & 14 \\ \hline \text{S} & 4 & 10 & 13 \\ \hline \end{array}\]
Which of these contractors is more certain about completing the job in time?
Step 1: PERT analysis variance formula.
The variance of activity time in PERT (Program Evaluation and Review Technique) is calculated using the formula: \[\sigma^2 = \left(\frac{t_p - t_o}{6}\right)^2\] A lower variance indicates greater certainty regarding the job completion time.
Step 2: Calculate variance for each contractor.
- Contractor P: \[\sigma^2 = \left(\frac{13 - 5}{6}\right)^2 = \left(\frac{8}{6}\right)^2 = 1.78\] - Contractor Q: \[\sigma^2 = \left(\frac{12 - 6}{6}\right)^2 = \left(\frac{6}{6}\right)^2 = 1.00\] - Contractor R: \[\sigma^2 = \left(\frac{14 - 5}{6}\right)^2 = \left(\frac{9}{6}\right)^2 = 2.25\] - Contractor S: \[\sigma^2 = \left(\frac{13 - 4}{6}\right)^2 = \left(\frac{9}{6}\right)^2 = 2.25\]
Step 3: Comparison of variances.
- P: Variance = 1.78
- Q: Variance = 1.00 (This is the lowest variance)
- R: Variance = 2.25
- S: Variance = 2.25
Step 4: Conclusion.
Contractor Q exhibits the smallest variance, which means Q is the most certain contractor regarding timely job completion.
Which of the following statements (pertaining to CPM network analysis) are correct?
A. It is an event-oriented method.
B. It is an activity-oriented method.
C. Time and cost are controlling factors.
D. Time alone is the controlling factor.
Choose the most appropriate answer from the options given below: