Question:medium

The network diagram of a construction project is shown in the following Figure. The duration of each activity, in days, and the early start time of the project are denoted in the diagram. The total project duration along the critical path, in days, is _____(in integer).
The network diagram of a construction project is shown in the following Figure. The duration of each activity,

Updated On: Jan 13, 2026
Show Solution

Correct Answer: 18

Solution and Explanation

Correct answer: 18
Was this answer helpful?