A contractor committed to constructing a road in \(200\) days with \(140\) workers.
After \(60\) days, only \( \frac{1}{4} \) of the road was completed.
This indicates the remaining work is:
\( 1 - \frac{1}{4} = \frac{3}{4} \)
The time remaining to complete the outstanding work is:
\( 200 - 60 = 140 \) days.
Let \( x \) represent the number of additional workers needed to finish the remaining work within the allocated time.
The governing formula is:
where:
Applying the formula to both phases:
Work completed in the initial \(60\) days by \(140\) individuals:
Cross-multiplying yields:
\[140 \times 60 \times 4 = (140 + x) \times 140 \times \frac{4}{3}\]The left-hand side simplifies to:
\[140 \times 60 \times 4 = 33600\]The right-hand side is:
\[\frac{4}{3} \times 140 \times (140 + x)\]Equating both sides:
\[33600 = \frac{4}{3} \times 140 \times (140 + x)\]Dividing both sides by \(4\):
\[8400 = \frac{1}{3} \times 140 \times (140 + x)\]Multiplying both sides by \(3\):
\[25200 = 140 \times (140 + x)\]Dividing both sides by \(140\):
\[\frac{25200}{140} = 140 + x \Rightarrow 180 = 140 + x\]Consequently,
\[x = 180 - 140 = 40\]Therefore, \(40\) additional workers are required to complete the work on schedule.
A box contains 16 red, 12 white, and 15 yellow identical marbles. A man picks one marble at a time without replacement. How many times must he pick a marble to be 100% certain of picking at least 3 white marbles?