Question:medium

Rahul, Rakshita and Gurmeet, working together, would have taken more than 7 days to finish a job. On the other hand, Rahul and Gurmeet, working together would have taken less than 15 days to finish the job. However, they all worked together for 6 days, followed by Rakshita, who worked alone for 3 more days to finish the job. If Rakshita had worked alone on the job then the number of days she would have taken to finish the job, cannot be

Updated On: Nov 25, 2025
  • 16
  • 21
  • 17
  • 20
Hide Solution

The Correct Option is B

Solution and Explanation

Let the work rates of Rahul, Rakshita, and Gurmeet be $a$, $b$, and $c$ units of work per day, respectively.

Let the total work be $W$. 

According to the problem statement:
 

  • The three individuals worked collaboratively for 6 days.
  • Rakshita independently completed the remaining work in an additional 3 days.

The total work done can be expressed as:
$W = 6(a + b + c) + 3b$    --- (1) 

Additional information provided:
 

  • The work could not be completed by all three individuals together in 7 days:
    $7(a + b + c) < W$    --- (2)
  • Rahul and Gurmeet working together would have completed the work in less than 15 days:
    $15(a + c) > W$    --- (3)

Combining inequalities (2) and (3) yields:
$15(a + c) < W < 7(a + b + c)$    --- (4) 

Substitute equation (1) into inequality (4): 
$15(a + c) < 6(a + b + c) + 3b < 7(a + b + c)$ 

Simplify the middle expression:
$6(a + b + c) + 3b = 6a + 6b + 6c + 3b = 6a + 9b + 6c$ 

Now, analyze the two resulting inequalities:
$15(a + c) < 6a + 9b + 6c$    --- (5) 
$6a + 9b + 6c < 7(a + b + c)$    --- (6) 

Expand the right side of inequality (6): 
$7(a + b + c) = 7a + 7b + 7c$ 

Rewrite inequality (6) with the expanded term:
$6a + 9b + 6c < 7a + 7b + 7c$ 
Subtracting terms from both sides results in:
$-a + 2b - c < 0 \implies a + c > 2b$    --- (7) 

Simplify inequality (5): 
$15(a + c) < 6a + 9b + 6c$
$ \Rightarrow 15a + 15c < 6a + 9b + 6c$
$ \Rightarrow 9a + 9c < 9b$
$ \Rightarrow a + c < b$    --- (8) 

The derived inequalities are:

  • From (7): $a + c > 2b$
  • From (8): $a + c < b$

Inequality (8) contradicts inequality (7), indicating a calculation error occurred previously. 
Re-evaluating inequality (5) accurately: 

$15(a + c) < 6a + 9b + 6c$
$ \Rightarrow 15a + 15c < 6a + 9b + 6c$
$ \Rightarrow 9a + 9c < 9b$
$ \Rightarrow a + c < b$    This result still contradicts (7), suggesting an earlier sign error. 

Let's reconcile the findings from the inequalities. Using the relationships derived from the problem constraints:
From $7(a + b + c)<W$ and $W<15(a + c)$, we infer:

  • $7(a + b + c)<15(a + c)$

From $W = 6(a + b + c) + 3b$, and $W<7(a + b + c)$: $6(a + b + c) + 3b<7(a + b + c)$ $6a + 6b + 6c + 3b<7a + 7b + 7c$ $6a + 9b + 6c<7a + 7b + 7c$ $2b<a + c$    --- (7') (Corrected inequality (7))

From $W = 6(a + b + c) + 3b$, and $W>15(a + c)$: $6(a + b + c) + 3b>15(a + c)$ $6a + 6b + 6c + 3b>15a + 15c$ $6a + 9b + 6c>15a + 15c$ $9b>9a + 9c$ $b>a + c$    --- (8') (Corrected inequality (8))

Combining the corrected inequalities (7') and (8'):
We have $b>a + c$ and $a + c>2b$. This implies $b>2b$, which is only possible if $b$ is negative, which is not feasible for a work rate. 

Let's re-examine the inequalities from the prompt statement:
$7(a + b + c)<W$ and $15(a + c)>W$. This implies $7(a+b+c)<15(a+c)$. $7a + 7b + 7c<15a + 15c$ $7b<8a + 8c$. 

Using $W = 6(a + b + c) + 3b$: From $W<7(a+b+c)$: $6(a+b+c) + 3b<7(a+b+c)$ $6a + 9b + 6c<7a + 7b + 7c$ $2b<a+c$. From $W>15(a+c)$: $6(a+b+c) + 3b>15(a+c)$ $6a + 9b + 6c>15a + 15c$ $9b>9a + 9c$ $b>a+c$.

The derived inequalities are $2b<a+c$ and $b>a+c$. These inequalities are contradictory. Let's reconsider the initial problem statement implications.

If $7(a+b+c)<W$, then $W/7>a+b+c$. If $15(a+c)>W$, then $W/15<a+c$. If Rakshita worked alone for 3 days to finish, $3b = W - 6(a+b+c)$. So $b = (W - 6(a+b+c))/3 = W/3 - 2(a+b+c)$.

Substitute $a+c$ from $W/15<a+c$: $b>W/15$. Substitute $a+b+c$ from $W/7>a+b+c$: $b = W/3 - 2(a+b+c)>W/3 - 2(W/7) = W/3 - 2W/7 = (7W - 6W)/21 = W/21$.

So, $b>W/15$ and $b>W/21$. The tighter lower bound is $b>W/15$.

Now consider the upper bound for $b$. From $7(a+b+c)<W$, we have $a+b+c<W/7$. From $W = 6(a+b+c) + 3b$, we have $3b = W - 6(a+b+c)$. $3b>W - 6(W/7) = W - 6W/7 = W/7$. $b>W/21$. This confirms the lower bound.

From $15(a+c)>W$, we have $a+c>W/15$. $W = 6a + 6b + 6c + 3b = 6(a+c) + 6b + 3b = 6(a+c) + 9b$. Since $a+c>W/15$, $W = 6(a+c) + 9b>6(W/15) + 9b = 2W/5 + 9b$. $W - 2W/5>9b$ $3W/5>9b$ $b<3W/45 = W/15$.

So we have $b>W/21$ and $b<W/15$. Therefore, $b$ lies in the range $\dfrac{W}{21} < b < \dfrac{W}{15}$. This means the number of days for Rakshita is between 15 and 21. 

The correct answer is (B): 15 to 21 days.

 

Was this answer helpful?
0

Top Questions on Time and Work