Question:medium

Gautam and Suhani, working together, can finish a job in 20 days. If Gautam does only 60% of his usual work on a day, Suhani must do 150% of her usual work on that day to exactly make up for it. Then, the number of days required by the faster worker to complete the job working alone is

Updated On: Nov 25, 2025
  • 30
  • 36
  • 70
  • None of Above
Hide Solution

The Correct Option is B

Solution and Explanation

Let W represent the total work. Let g and s be the work efficiencies of Gautam and Suhani, respectively.
According to the problem statement:
$ \Rightarrow\ g + s = \frac{W}{20} $ (combined work per day) ……. (i)

Gautam works at 60% of his efficiency ($ \frac{3g}{5} $), and Suhani works at 150% of her efficiency ($ \frac{3s}{2} $).
Using these adjusted efficiencies, the combined work per day is:

$ \Rightarrow\ \frac{3g}{5} + \frac{3s}{2} = \frac{W}{20} $ (combined work per day)

Equating the two expressions for combined work per day:

$ \Rightarrow\ g + s = \frac{3g}{5} + \frac{3s}{2} $

Solving for the ratio of their efficiencies:

$ \Rightarrow\ \frac{s}{g} = \frac{4}{5} $

This indicates that Gautam is more efficient than Suhani.
Substituting the relationship $ s = \frac{4g}{5} $ into equation (i):

$ \Rightarrow\ g + \frac{4g}{5} = \frac{W}{20} $

Simplifying the left side:

$ \Rightarrow\ \frac{9}{5}g = \frac{W}{20} $

Solving for Gautam's individual efficiency:

$ \Rightarrow\ g = \frac{W}{36} $

Therefore, Gautam requires 36 days to complete the entire work.
The correct option is (B) : 36.

Was this answer helpful?
0

Top Questions on Time and Work