Question:medium

A contractor agreed to construct a 6 km road in 200 days. He employed 140 persons for the work. After 60 days, he realized that only 1.5 km road has been completed. How many additional people would he need to employ in order to finish the work exactly on time?

Updated On: Jan 15, 2026
Show Solution

Solution and Explanation

The direct relationship between the number of men, the amount of work (tunnel length), and time (days) is proportional, assuming other factors are constant. This can be represented as: \[ \text{Men} \times \text{Work} \propto \text{Time} \]

Given Data:

MenTunnel LengthDays
Initial1401.5 km60
RemainingX4.5 km140

Step-by-Step Calculation:

Using the direct proportion, we calculate the number of men (X) required for the remaining work:

\[ X = 140 \times \frac{4.5}{1.5} \times \frac{60}{140} \]

Simplifying the equation:

\[ X = 140 \times 3 \times \frac{60}{140} = 3 \times 60 = 180 \]

Therefore, the total number of men required for the remaining work is \( \boxed{180} \).

The number of additional men needed is the difference between the total required and the initial number of men:

\[ 180 - 140 = \boxed{40} \]


Final Answer:

40 additional men are necessary to complete the remaining 4.5 km tunnel within 140 days.

Was this answer helpful?
0


Questions Asked in CAT exam