| Activity | Connecting Events | Three PERT Times (in Days) |
|---|---|---|
| P | 1 to 2 | 4 - 6 - 8 |
| Q | 1 to 3 | 5 - 6 - 13 |
| R | 2 to 5 | 6 - 8 - 22 |
| S | 2 to 3 | 8 - 11 - 14 |
| T | 3 to 5 | 2 - 4 - 12 |
| U | 3 to 4 | 4 - 8 - 18 |
| V | 4 to 5 | 5 - 7 - 15 |
The time estimates obtained from four contractors (P, Q, R and S) for executing a particular job are as under:
\[\begin{array}{|c|c|c|c|} \hline \textbf{Contractor} & \textbf{Optimistic time, $t_o$} & \textbf{Most likely time, $t_m$} & \textbf{Pessimistic time, $t_p$} \\ \hline \text{P} & 5 & 10 & 13 \\ \hline \text{Q} & 6 & 9 & 12 \\ \hline \text{R} & 5 & 10 & 14 \\ \hline \text{S} & 4 & 10 & 13 \\ \hline \end{array}\]
Which of these contractors is more certain about completing the job in time?
Which of the following statements (pertaining to CPM network analysis) are correct?
A. It is an event-oriented method.
B. It is an activity-oriented method.
C. Time and cost are controlling factors.
D. Time alone is the controlling factor.
Choose the most appropriate answer from the options given below: