List of top Water Resources Engineering Questions on Flood estimation and routing

The probability (in %) that a storm having return period of 15 years may occur in the next 10 years is ______ (rounded off to two decimal places).
  • GATE CE - 2026
  • GATE CE
  • Water Resources Engineering
  • Flood estimation and routing
Types of flood routing and methods are given in the table below.
Column 1: Type of Flood RoutingColumn 2: Method
(P) Hydrologic routing(i) Muskingum method
(Q) Hydraulic routing(ii) Modified Pul's method
(R) Reservoir routing(iii) Method of Characteristics
(S) Channel routing

Option(s) giving the CORRECT match(es) between Column 1 and Column 2 is/are:
  • GATE CE - 2026
  • GATE CE
  • Water Resources Engineering
  • Flood estimation and routing
A bridge with an expected life of 50 years is designed for a flood of 10000 m\(^3\)/s corresponding to the return period of 100 years. The risk associated with this design is (rounded off to two decimal places).
  • GATE CE - 2026
  • GATE CE
  • Water Resources Engineering
  • Flood estimation and routing

The mean rainfall over a catchment has to be estimated. The data for four rain gauges located in and around the catchment is listed in the table. Which one of the following statements is correct: 

  • GATE CE - 2025
  • GATE CE
  • Water Resources Engineering
  • Flood estimation and routing