Question:medium

Ravi can do \( \frac{3}{4} \) of a work in 12 days. In how many days Ravi can finish the \( \frac{1}{2} \) work?

Show Hint

To calculate the time taken for a fraction of the work, use the ratio of the work done and the total time, then apply it to the desired fraction.
Updated On: Jan 15, 2026
  • 7 days
  • None of these
  • 8 days
  • 6 days
Show Solution

The Correct Option is D

Solution and Explanation

If the total work is \( W \), and Ravi finishes \( \frac{3}{4} \) of it in 12 days, the total time to complete the work is: \[ \text{Total time} = \frac{12}{3/4} = 16 \, \text{days} \] To find the time for \( \frac{1}{2} \) of the work: \[ \frac{1}{2} \times 16 = 8 \, \text{days} \] Thus, Ravi needs 8 days to complete \( \frac{1}{2} \) of the work.
Was this answer helpful?
0