Question:easy

Neha can complete a work in 6 days and Ishrat can complete the same work in 4 days. What will be the time taken by them to complete the same work together ?

Show Hint

Add daily work: \(1/6 + 1/4 = 5/12\), so time is \(12/5\) days.
Updated On: Oct 1, 2026
  • \(1\frac{2}{5}\) days
  • 3 days
  • \(2\frac{2}{5}\) days
  • 2 days
Show Solution

The Correct Option is C

Solution and Explanation

Step 1: Idea:
Pick a total amount of work that both times divide into. The LCM of 6 and 4 is 12, so take the work as 12 units.

Step 2: Work per day:
Neha: $12 \div 6 = 2$ units per day. Ishrat: $12 \div 4 = 3$ units per day. Together: 5 units per day.

Step 3: Time:
Time $= \dfrac{12}{5} = 2.4$ days, which is $2\frac{2}{5}$ days.

Step 4: Sense check:
The answer must be more than 2 days (half of the faster worker time is 2 days) and less than 4 days. 2.4 fits and matches option 3.

Final Answer:
The time taken together is $2\frac{2}{5}$ days. \[ \boxed{2\frac{2}{5} \text{ days}} \]