Question:medium

Consider the following unit operations; arrange them in sequence as performed during wet milling of pulses
A. Conditioning
B. Mixing with red earth
C. Soaking
D. Dehusking
E. Grading
Choose the correct answer from the options given below:

Show Hint

To find the sequence quickly in exams:
- Milling begins with Soaking (C).
- Milling ends with Dehusking (D) and then final Sorting/Grading (E).
This helps you identify the correct sequence starting with C and ending with E.
  • C, B, D, E, A
  • C, B, A, D, E
  • B, C, A, D, E
  • C, A, B, D, E
Show Solution

The Correct Option is B

Solution and Explanation