Question:medium

A wall of 60 m long can be built by 36 men in 21 days. Number of men required to build the same wall in 14 days, is

Show Hint

For constant work, use the relation: Men $\times$ Days = Constant.
Updated On: Mar 20, 2026
  • 50
  • 52
  • 54
  • 56
Show Solution

The Correct Option is C

Solution and Explanation

To solve this problem, we will use the concept of "man-days," which is a common term in work and time-related problems. The "man-days" refers to the product of the number of men and the number of days they work.

Let's break down the given information and find the solution step-by-step:

  1. First, calculate the total amount of work in terms of man-days that 36 men complete in 21 days to build a 60 m wall.
\[ \text{Total work (man-days)} = \text{Number of men} \times \text{Number of days} = 36 \times 21 \]
  1. Perform the multiplication to find the total work:
\[ \text{Total work} = 756 \text{ man-days} \]
  1. Now, we want to find the number of men required to do the same amount of work (756 man-days) in 14 days.
\[ \text{Number of men required} = \frac{\text{Total work}}{\text{Number of days}} = \frac{756}{14} \]
  1. Calculate the division to find the required number of men:
\[ \text{Number of men required} = 54 \]

Hence, 54 men are required to build the same wall in 14 days.

Therefore, the correct answer is 54.

Was this answer helpful?
0