To solve the problem of determining the number of days B requires to finish the job alone, we follow these steps:
- Let the work done by B in one day be \(1/x\) of the work.
- According to the problem, A is twice as efficient as B. Hence, the work done by A in one day is \(2/x\) of the work.
- When A and B work together, their combined work done in a day is the sum of their individual work per day. Therefore, A and B together complete \((2/x + 1/x) = 3/x\) of the work in one day.
- It is given that A and B together can finish the job in 12 days. Therefore, the work done by them together in one day is \(1/12\) of the work.
- Equating the total work done per day when working together to \(1/12\) of the work, we get: \(\frac{3}{x} = \frac{1}{12}\)
- Solving for \(x\):
- Cross-multiply to get \(3 \times 12 = x \times 1\), which simplifies to \(x = 36\).
- The number of days B requires to finish the job alone is 36 days.
Thus, the correct answer is 36 days.