Question:medium

A completes \( \frac{7}{10} \) of a work in 15 days and then he completes the remaining work with the help of B in 5 days. In how many days can A and B together complete the entire work?

Show Hint

When working with rates, combine the rates of individuals working together to find the total work rate, and then calculate the time needed to complete the task.
Updated On: Mar 7, 2026
  • 13 \( \frac{1}{3} \)
  • 15 \( \frac{3}{4} \)
  • 14 \( \frac{1}{4} \)
  • 16 \( \frac{2}{3} \)
Show Solution

The Correct Option is A

Solution and Explanation

Step 1: A's Work Rate.
A completes \( \frac{7}{10} \) of the work in 15 days. A's daily work rate is calculated as:\[\text{Work rate of A} = \frac{7}{10} \div 15 = \frac{7}{150}\]

Step 2: B's Work Rate.
The remaining work is \( 1 - \frac{7}{10} = \frac{3}{10} \). This remaining work is completed by A and B together in 5 days. Their combined daily work rate is:\[\text{Work rate of A and B} = \frac{3}{10} \div 5 = \frac{3}{50}\]To find B's work rate, subtract A's work rate from their combined rate:\[\text{Work rate of B} = \frac{3}{50} - \frac{7}{150} = \frac{9}{150} - \frac{7}{150} = \frac{2}{150} = \frac{1}{75}\]

Step 3: Total Time to Complete the Work.
The combined work rate of A and B is the sum of their individual rates:\[\text{Work rate of A and B together} = \frac{7}{150} + \frac{1}{75} = \frac{7}{150} + \frac{2}{150} = \frac{9}{150} = \frac{3}{50}\]The total time required to complete the entire work is the reciprocal of their combined work rate:\[\text{Time} = \frac{1}{\text{Work rate of A and B together}} = \frac{50}{3} = 13 \frac{1}{3} \, \text{days}\]

Final Answer: \[ \boxed{13 \frac{1}{3} \, \text{days}} \]

Was this answer helpful?
0