Question:easy

A certain number of people were supposed to complete a work in 24 days. The work, however, took 32 days, since 9 people were absent throughout. How many people were supposed to be working originally?

Show Hint

Total work (people times days) stays constant; equate 24 times the original people to 32 times the people who actually worked.
Updated On: Jul 16, 2026
  • 32
  • 27
  • 36
  • 30
Show Solution

The Correct Option is C

Solution and Explanation

Since the total amount of work does not change, the number of people needed is inversely proportional to the number of days taken.

  1. Set up the inverse proportion. If $x$ is the original number of people (planned for 24 days) and $x - 9$ people actually worked for 32 days, then $\dfrac{x}{x-9} = \dfrac{32}{24} = \dfrac{4}{3}$.
  2. Cross-multiply. $3x = 4(x - 9) = 4x - 36$.
  3. Solve for $x$. $3x - 4x = -36 \Rightarrow -x = -36 \Rightarrow x = 36$.
  4. Verify. $24 \times 36 = 864$ man-days, and $32 \times (36 - 9) = 32 \times 27 = 864$ man-days. Both match.

So 36 people were originally supposed to work, option C.

Was this answer helpful?
0

Top Questions on Time and Work


Questions Asked in SNAP exam