Step 1: Take the whole work as 24 units (LCM of 6, 8 and 2). A's rate \(=24/6=4\) units/day, B's rate \(=24/8=3\) units/day, and A+B+C together \(=24/2=12\) units/day, so C's rate \(=12-4-3=5\) units/day.
Step 2: In 2 days, A does \(2\times4=8\) units, B does \(2\times3=6\) units, C does \(2\times5=10\) units, totalling \(8+6+10=24\) units, which checks out.
Step 3: Payment is split in the ratio of work done, \(8:6:10=4:3:5\), with total parts \(12\). A's share \(=\dfrac{4}{12}\times720=240\). \[ \boxed{240} \]