Question:medium

A can complete a work in 12 days and B can complete it in 18 days. In how many days will they complete the work together?

Show Hint

When two people work together, the total time will always be less than the time taken by the fastest person alone. Since A takes 12 days, the answer must be less than 12 (which all options are, but it's a good sanity check!).
Updated On: May 30, 2026
  • 6 days
  • 7.2 days
  • 8 days
  • 9 days
Show Solution

The Correct Option is B

Solution and Explanation

Step 1: Understanding the Concept:
When people work together, their daily work rates are added to determine the combined efficiency.
Rate is the inverse of the time taken to complete the task.
Step 2: Key Formula or Approach:
If A takes \( x \) days and B takes \( y \) days, the time taken together (\( T \)) is:
\[ T = \frac{xy}{x+y} \] Alternatively, you can add their one-day work: \( \frac{1}{x} + \frac{1}{y} = \frac{1}{T} \).
Step 3: Detailed Explanation:
Given values:
Time for A (\( x \)) = 12 days.
Time for B (\( y \)) = 18 days.
Using the shortcut formula:
\[ T = \frac{12 \times 18}{12 + 18} \] \[ T = \frac{216}{30} \] Simplify the fraction:
\[ T = \frac{216 \div 3}{30 \div 3} = \frac{72}{10} \] \[ T = 7.2 \text{ days} \] So, working together, they take 7.2 days to complete the job.
Step 4: Final Answer:
They will complete the work together in 7.2 days.
Was this answer helpful?
3

Top Questions on Time and Work


Questions Asked in CUET (UG) exam