After 5 days, the 12 men have enough work left for another 15 days (\(12 \times 15\) man-days).
Since the workforce is halved (from 12 men to 6 men), the time taken to complete the remaining work must double:
\(15 \text{ days} \times 2 = 30 \text{ days}\). No heavy calculation is needed!