The three phases involved in the management of large projects are:

Show Hint

Think of the "PSC" mnemonic: Plan it, Schedule it, Control it. If you aren't controlling the project after it starts, the planning and scheduling were useless!
Updated On: May 20, 2026
  • Planning, scheduling, evaluating
  • Planning, scheduling, controlling
  • Scheduling, designing, operating
  • Scheduling, operating, evaluating
Show Solution

The Correct Option is B

Solution and Explanation