Question:easy

The step of controlling process which reveals the deviation between actual performance and desired results is :

Show Hint

The gap between actual and planned results shows up only when the two are compared. That is the comparison step, not the setting, analysing or correcting steps.
Updated On: Oct 26, 2026
  • Setting performance standards
  • Analysing deviations
  • Taking corrective action
  • Comparing actual performance with the standards
Show Solution

The Correct Option is D

Solution and Explanation

Step 1: Think of a simple example:
A school plans 90 percent attendance. By month end the register shows 80 percent.
The difference of 10 percent appears only when the register is compared with the plan.

Step 2: Apply it to the controlling process:
In the same way, a manager sees the deviation only at the step where actual performance is compared with the standard.
That is option (D).

Step 3: Check each option against its job:
(A) Setting standards: it creates the benchmark but does not show any gap.
(B) Analysing deviations: it begins once the gap is known and looks for its causes. It does not reveal the gap itself.
(C) Taking corrective action: it is the remedy step and follows the analysis.

Final Answer:
Comparing actual performance with the standards reveals the deviation, so option (D) is correct.
Was this answer helpful?
0