Because contract costing projects often span multiple years, contractors use the following formula to value the Work-in-Progress (WIP) asset on their balance sheets:
$$\text{Value of WIP} = \text{Value of Work Certified} + \text{Cost of Work Uncertified} - \text{Cash Received from Contractee}$$