Question:medium

The work shall be judged by contractee's architect, surveyor or engineer who issue a certificate, stating the value of work done so far. This certificate is called:

Show Hint

The value of Work Certified is credited to the Contract Account and shown as work-in-progress on the asset side of the balance sheet.
Updated On: Jun 17, 2026
  • General work
  • Work certified
  • Work uncertified
  • Managerial work
Show Solution

The Correct Option is B

Solution and Explanation

Was this answer helpful?