Step 1: Think about how a plan is built:
A time plan is built like a timetable. We start with what is to be done and end by checking if it works.
Step 2: Four steps in order:
1. Make a list of all the activities Meena has to do.
2. Separate the fixed activities (such as school) from the flexible ones (such as chores).
3. Allot the time that each activity needs.
4. Balance the plan so that there is time for study, work and rest.
Step 3: Why the order matters:
We cannot allot time before knowing the activities, and we cannot balance the day before knowing the time each activity takes.
Step 4: Check:
A fifth step, evaluating the plan, can also be used. Any four steps give full marks.
Final Answer:
The four steps are listing, grouping, estimating time and balancing.
\[\boxed{\text{List, group, estimate time, balance}}\]