Question:medium

In PERT technique, the time estimate of activities and probability of their occurrence follows:

Show Hint

Expected time ($t_e$) for the Beta distribution is calculated as: $t_e = \frac{t_o + 4t_m + t_p}{6}$. Note how the "Most Likely" time is weighted four times more than the extremes!
Updated On: May 20, 2026
  • Gumbel distribution
  • Beta distribution
  • Poisson distribution
  • Normal distribution
Show Solution

The Correct Option is B

Solution and Explanation