Question:
medium
In network analysis using the Critical Path Method (CPM), the critical path is the one with
Show Hint
Critical path characteristics: \[ \boxed{ \text{Longest Duration} \quad\text{and}\quad \text{Zero Float}. } \]
TS PGECET - 2026
TS PGECET
Updated On:
Jul 14, 2026
The longest duration
Total float
Maximum resources
Negative float
Show Solution
The Correct Option is
A
Solution and Explanation
Download Solution in PDF
Was this answer helpful?
0
Top Questions on Systems Engineering
The primary objective of a balanced transportation problem is to
TS PGECET - 2026
Mining Engineering
Systems Engineering
View Solution
The assignment problem is a special case of the transportation problem where
TS PGECET - 2026
Mining Engineering
Systems Engineering
View Solution
In network analysis using the Critical Path Method (CPM), the critical path is the one with
TS PGECET - 2026
Mining Engineering
Systems Engineering
View Solution
In decision theory, which criterion assumes the decision-maker is pessimistic?
TS PGECET - 2026
Mining Engineering
Systems Engineering
View Solution
Want to practice more? Try solving extra ecology questions today
View All Questions
Questions Asked in TS PGECET exam
The Eigenvalues of \(3\times 3\) real matrix A are 1, 2, 3 then \(A^{-1} =\)
TS PGECET - 2026
Linear Algebra
View Solution
Let \(A=\begin{bmatrix} 1 & 1 & 0 \\ 0 & 1 & 1 \\ 0 & 0 & 1 \end{bmatrix}\). If \(u_1\) and \(u_2\) are column matrices such that \(Au_1 = \begin{bmatrix} 2 \\ 1 \\ 0 \end{bmatrix}\) and \(Au_2 = \begin{bmatrix} 1 \\ 0 \\ 1 \end{bmatrix}\), then \(u_1 - u_2\) is
TS PGECET - 2026
Matrices
View Solution
Let \(a,b\) and \(c\) be real numbers. Suppose there exist real numbers \(x,y,z\) which are not all zero such that the system of equations \(x = cy + bz\), \(y = cx + az\) and \(z = bx + ay\) has a non-zero solution then \(\left(a+b+c\right)^2 =\)
TS PGECET - 2026
Determinants
View Solution
For the function \(f(x)=\log x\), the number \(c\) strictly between \(e^2\) and \(e^3\) that satisfies \(f'(c)=\dfrac{f(e^3)-f(e^2)}{e^3-e^2}\) is
TS PGECET - 2026
Calculus
View Solution
The directional derivative of \(f(x,y,z)=4e^{2x-y+z}\) at the point \((1,1,-1)\) in the direction of the vector \(\vec{a}=-4\hat{i}+4\hat{j}+7\hat{k}\) is
TS PGECET - 2026
Vector Calculus
View Solution