Question:medium

In network analysis using the Critical Path Method (CPM), the critical path is the one with

Show Hint

Critical path characteristics: \[ \boxed{ \text{Longest Duration} \quad\text{and}\quad \text{Zero Float}. } \]
Updated On: Jul 14, 2026
  • The longest duration
  • Total float
  • Maximum resources
  • Negative float
Show Solution

The Correct Option is A

Solution and Explanation