Question:medium

In load flow studies, PV bus is treated as a PQ bus, when :

Show Hint

PV Bus changes to PQ Bus when: \[ Q \text{ violates generator reactive power limits} \]
Updated On: May 22, 2026
  • Reactive power goes beyond limits
  • Phase angle becomes high
  • Voltage limit is violated
  • Active power limit is violated
Show Solution

The Correct Option is A

Solution and Explanation