Question:easy

‘Green Tech Solutions’, a renewable energy company, set a target of reducing its production cost by 15% in the current financial year. After a few months, the management reviews the progress and finds that the cost reduction measures implemented have not been as effective as planned. By reviewing the progress ‘Green Tech Solutions’ has completed one of the steps of controlling process.

Identify the step of controlling process from the following :

Show Hint

A review of progress against a target means putting actual results beside the standard. Name that step of controlling.
Updated On: Nov 11, 2026
  • Setting performance standards
  • Comparing actual performance with standards
  • Analysing deviations
  • Taking corrective actions
Show Solution

The Correct Option is B

Solution and Explanation

Step 1: Read the key line:
The key line is that management "reviews the progress and finds" that the measures were not as effective as planned.
A review of progress against a target is a comparison.

Step 2: Check option (A):
Setting standards means fixing the target. The 15% cost cut was already set at the start of the year. So (A) is wrong.

Step 3: Check option (B):
Comparing actual performance with standards means putting the real results next to the target and seeing how far apart they are.
The management does exactly this when it finds the results short of the plan. So (B) is right.

Step 4: Check options (C) and (D):
Analysing deviations comes after the comparison, when the cause of the gap is studied. The case does not talk of any cause.
Taking corrective actions is the last step, where changes are made. No change is described in the case. So (C) and (D) are wrong.

Final Answer:
The review of progress against the cost target is the step of comparing actual performance with standards, which is option (B).
Was this answer helpful?
0