Question:easy

Calculate the cumulative pan evaporation (CPE) required for scheduling irrigation at an \(IW/CPE\) ratio of \(0.5\), given \(5\) cm of irrigation water (IW).

Show Hint

Use \(CPE = IW / \text{ratio}\) to find the pan evaporation depth.
  • 5 cm
  • 10 cm
  • 15 cm
  • 20 cm
Show Solution

The Correct Option is B

Solution and Explanation

Concept:
The IW/CPE ratio approach schedules irrigation by comparing how much water is applied against how much water the pan has lost through evaporation. A ratio of 0.5 means for every 1 cm of pan evaporation, only 0.5 cm of irrigation water gets applied over the same period, or equivalently the irrigation depth is half the cumulative evaporation depth.


Step 1: Set up the relation.

\[ IW = 0.5 \times CPE \]


Step 2: Substitute the known irrigation depth.

We are told \(IW = 5\) cm, so:
\[ 5 = 0.5 \times CPE \]


Step 3: Solve for CPE.

\[ CPE = \frac{5}{0.5} = 10 \text{ cm} \]
Checking it back: half of 10 cm is 5 cm, which matches the given irrigation depth, so the number is consistent.


Step 4: Final answer.

\[ \boxed{CPE = 10 \text{ cm}} \]