Arrange the following stages of engineering surveys to be done for a new highway alignment project in the correct sequence:
A. Reconnaissance
B. Map study
C. Preliminary survey
D. Final location
E. Detailed survey
Choose the correct answer from the options given below :

Show Hint

Mnemonic: "M-R-P-F-D". Map study is always first, and Detailed survey is always last. Reconnaissance is the first "field" activity.
Updated On: May 20, 2026
  • A, B, C, D, E
  • C, B, A, D, E
  • B, A, C, D, E
  • B, C, A, D, E
Show Solution

The Correct Option is C

Solution and Explanation