3.75
The objective is to determine the duration B requires to complete the outstanding work after a period of collaboration with A.
- Work Rate: An individual completing a task in 'n' days has a daily work contribution of \( \frac{1}{n} \).
- Aggregate Effort: When multiple individuals collaborate, their combined daily work is the sum of their individual daily contributions.
- Unfinished Work: This is calculated by subtracting the work already completed from the total task (considered as 1 unit).
- A's work completion time: 12 days → A's daily work rate = \( \frac{1}{12} \)
- B's work completion time: 15 days → B's daily work rate = \( \frac{1}{15} \)
- Joint work duration: 5 days
Combined daily work rate = \( \frac{1}{12} + \frac{1}{15} = \frac{5 + 4}{60} = \frac{9}{60} = \frac{3}{20} \)
Work completed over 5 days = \( 5 \times \frac{3}{20} = \frac{15}{20} = \frac{3}{4} \)
Remaining work = \( 1 - \frac{3}{4} = \frac{1}{4} \)
B's daily work rate = \( \frac{1}{15} \)
Time required by B = \( \frac{\frac{1}{4}}{\frac{1}{15}} = \frac{15}{4} = 3.75 \) days
B will require 3.75 days (equivalent to 3 days and 3 hours) to finalize the remaining portion of the task.
A box contains 16 red, 12 white, and 15 yellow identical marbles. A man picks one marble at a time without replacement. How many times must he pick a marble to be 100% certain of picking at least 3 white marbles?