1. Home
  2. Mine Planning

Filters

Found 1 Question

Set Default
Exams
Subjects
Topics

List of top Mine Planning Questions on PERT Network Analysis

The expected time (P days) and standard deviation (Q days) of the different activities (A to F) in a project are indicated in the network diagram as (P, Q). The standard deviation of the project completion time, in days, is . (Rounded off to one decimal place)

  • GATE MN - 2026
  • GATE MN
  • Mine Planning
  • PERT Network Analysis
contact us
terms & conditions
Privacy & Policy
© 2026 Patronum Web Private Limited