This question tests the basic definitions of cant deficiency and cant excess used in railway curve design. Both terms compare the cant actually laid on the track to the equilibrium cant that the train's running speed calls for.
The equilibrium speed is the speed at which the actual cant exactly balances the centrifugal force. Any speed above it creates a deficiency of cant, any speed below it creates an excess of cant, regardless of which physical line (main or branch) the train happens to be on.
Let's summarize:
So the correct statement is option (A).
Which of the following statements is/are INCORRECT?