Question:medium

Which method/technique is used to analyze the tasks involved in completing a given project, especially the time needed to complete each task, and identifying the minimum time needed to complete the total project?

Show Hint

CPM is useful in project management to ensure that the project is completed in the least amount of time while meeting deadlines.
Updated On: Feb 18, 2026
  • Critical Path Method (CPM)
  • Programme Evaluation and Review Technique (PERT)
  • Event Chain methodology
  • Gantt charts
Show Solution

The Correct Option is A

Solution and Explanation

CPM (Critical Path Method) pinpoints critical project tasks, determines the shortest possible project timeline, and optimizes task order to guarantee on-time completion.