What is the use of ‘dummy' in CPM network.
• [A.] To give a start, that is a starting activity
• [B.] To give logical representation in a network having an activity common in two operations running parallel to each other
• [C.] To prevent two arrows having common beginning and end points
• [D.] To represent the longest time taking activity in the network
• [E.] To represent the shortest path of the network Choose the correct answer from the options given below :