Question:medium

The Slack time in PERT analysis

Show Hint

Critical events and activities always have zero slack (or float). Non-critical events have positive slack.
Updated On: Jul 23, 2026
  • Can never be greater than zero
  • Is always zero for critical activities
  • Can never be less than zero
  • Is minimum for critical events
Show Solution

The Correct Option is D

Solution and Explanation