The reduction in project time normally results in

Show Hint

When shortening the project timeline, both direct and indirect costs tend to increase due to additional resources and overheads.
Updated On: Feb 19, 2026
  • Increasing the direct cost and decreasing the indirect cost
  • Decreasing the direct cost and increasing the indirect cost
  • Increasing the direct cost and the indirect cost both
  • Decreasing the direct cost and the indirect cost both
Show Solution

The Correct Option is C

Solution and Explanation

Step 1: Time and Cost Analysis.
Shortening project duration usually requires more resources, leading to higher direct (labor, materials) and indirect (overhead, supervision) costs.
Step 2: Summary.
Consequently, reducing project time typically increases both direct and indirect costs, making option (3) the correct choice.

Final Answer: \[ \boxed{3. \, \text{Increasing the direct cost and the indirect cost both}} \]