Increasing the direct cost and decreasing the indirect cost
Decreasing the direct cost and increasing the indirect cost
Increasing the direct cost and the indirect cost both
Decreasing the direct cost and the indirect cost both
Show Solution
The Correct Option isC
Solution and Explanation
Step 1: Time and Cost Analysis.
Shortening project duration usually requires more resources, leading to higher direct (labor, materials) and indirect (overhead, supervision) costs.
Step 2: Summary.
Consequently, reducing project time typically increases both direct and indirect costs, making option (3) the correct choice.
Final Answer:
\[
\boxed{3. \, \text{Increasing the direct cost and the indirect cost both}}
\]