The number of days required by three persons A, B, C independently to complete a given work is as per the ratio \(3:4:6\). How many days are required for B and C together to complete the work?
Statements:
(I) A is \(100\%\) more efficient than C.
(II) C requires 27 days more than A to complete the work.
Show Hint
In time and work problems, ratios only give relative values. To find exact time, always determine the multiplying factor.