Question:medium

The criterion that is specifically mentioned in Special Conditions of Contract (SCC) is \underline{\hspace{1cm}}.

Show Hint

In contracts, remember: GCC covers general/legal aspects, while SCC covers project-specific clauses like mobilization advance, payment schedules, and deadlines.
Updated On: Jan 13, 2026
  • Scope and performance of the work
  • Site mobilization advance
  • Labour regulation
  • Arbitration and law
Show Solution

The Correct Option is B

Solution and Explanation

Step 1: Understanding Special Conditions of Contract (SCC).
- SCC are supplementary clauses to the General Conditions of Contract (GCC).
- They address unique project requirements, particularly financial, mobilization, and site-specific stipulations.

Step 2: Evaluating Options.
- (A) Scope and performance of work → covered by a general clause in GCC.
- (B) Site mobilization advance → specifically addressed in SCC due to its project-specific nature and variability.
- (C) Labour regulation → typically falls under labor laws and compliance, not SCC-specific.
- (D) Arbitration and law → generally found in GCC.

Step 3: Determination.
Consequently, site mobilization advance is the correct criterion found in SCC. \[\boxed{\text{Site mobilization advance}}\]