Question:medium

The correct order of series of operations to be carried out in production planning control is:

Show Hint

Remember the classic PPC acronym sequence: R-S-D-F (Routing $\rightarrow$ Scheduling $\rightarrow$ Dispatching $\rightarrow$ Follow up).
Updated On: Jul 9, 2026
  • Dispatching -- Routing -- Scheduling -- Follow up
  • Routing -- Scheduling -- Follow up -- Dispatching
  • Routing -- Scheduling -- Dispatching -- Follow up
  • Scheduling -- Routing -- Dispatching -- Follow up
Show Solution

The Correct Option is C

Solution and Explanation

Was this answer helpful?