Question:medium

PERT technique deals with the project of

Show Hint

PERT is used for projects with uncertain timelines where task durations are variable and follow a probabilistic distribution
Updated On: Jan 17, 2026
  • probabilistic nature
  • deterministic nature
  • non-repetitive nature
  • repetitive nature
Show Solution

The Correct Option is A

Solution and Explanation

The Program Evaluation and Review Technique (PERT) is a method for projects with uncertain durations. It accounts for variability in task completion times, using statistical methods to estimate project duration and associated probabilities.