Contract frustration and force majeure are separate legal ideas. Both deal with the inability to fulfill a contract, but frustration arises automatically under the law, while force majeure is based on the contract's terms.
The correct answer is (C): ‘Frustration of contract’ and ‘force majeure’ are incorrectly presented as identical.
The case of Satyabrata Ghose v. Mugneeram Bangur Co. is a key ruling in Indian law regarding the legal principle of frustration, which deals with contracts becoming impossible to fulfill. The accurate answer is (B): Satyabrata Ghose v. Mugneeram Bangur & Co., 1954 SCR 310.
Courts generally cannot excuse a party from fulfilling a contract simply because it's become difficult; contract frustration demands impossibility or illegality.
The correct choice is (A): Courts can generally release a party from its contractual obligations if unforeseen events make performance excessively burdensome.
According to the Energy Watchdog ruling, a contract isn't frustrated just because costs rise, because fulfilling the contract at a higher cost remains possible.
The right answer is (A): The contract could still be carried out in different ways, even if it cost more, which meant the entire contract wasn't frustrated.
The principle of *lex non cogit ad impossibilia* means "the law doesn't force someone to do what's impossible," highlighting that the law won't demand the fulfillment of impossible duties.
The correct answer is (D): The law does not compel a promisor to do that which is impossible to perform.