Comprehension
Indeed, in England, in the celebrated Sea Angel case, 2013 (1) Lloyds Law Report 569, the modern approach to frustration is well put, and the same reads as under: “In my judgment, the application of the doctrine of frustration requires a multi-factorial approach. Among the factors that have to be considered are the terms of the contract itself, its matrix or context, the parties’ knowledge, expectations, assumptions and contemplations, in particular as to risk, as at the time of the contract, at any rate so far as these can be ascribed mutually and objectively, and then the nature of the supervening event, and the parties’ reasonable and objectively ascertainable calculations as to the possibilities of future performance in the new circumstances. Since the subject matter of the doctrine of frustration is contract, and contracts are about the allocation of risk, and since the allocation and assumption of risk is not simply a matter of express or implied provision but may also depend on less easily defined matters such as “the contemplation of the parties”, the application of the doctrine can often be a difficult one. In such circumstances, the test of “radically different” is important: it tells us that the doctrine is not to be lightly invoked; that mere incidence of expense or delay or onerousness is not sufficient; and that there has to be as it were a break in identity between the contract as provided for and contemplated and its performance in the new circumstances.”
“… It is clear from the above that the doctrine of frustration cannot apply to these cases as the fundamental basis of the PPAs remains unaltered. Nowhere do the PPAs state that coal is to be procured only from Indonesia at a particular price. In fact, it is clear on a reading of the PPA as a whole that the price payable for the supply of coal is entirely for the person who sets up the power plant to bear. The fact that the fuel supply agreement has to be appended to the PPA is only to indicate that the raw material for the working of the plant is there and is in order. It is clear that an unexpected rise in the price of coal will not absolve the generating companies from performing their part of the contract for the very good reason that when they submitted their bids, this was a risk they knowingly took. We are of the view that the mere fact that the bid may be non-escalable does not mean that the respondents are precluded from raising the plea of frustration, if otherwise it is available in law and can be pleaded by them. But the fact that a non-escalable tariff has been paid for, for example, in the Adani case, is a factor which may be taken into account only to show that the risk of supplying electricity at the tariff indicated was upon the generating company”. 
[Extracted from Energy Watchdog v. Central Electricity Regulatory Commission (2017) 14 SCC 80].
Question: 1

Which of the following is incorrect about a force majeure clause?

Updated On: Jan 13, 2026
  • The burden of proving the applicability of a force majeure clause rests on the party seeking to invoke it.
  • A force majeure clause ensures that non-performance is no breach because no performance was due in the circumstances which have occurred.
  • ‘Frustration of contract’ and ‘force majeure’ are indeed one and the same concept.
  • Force majeure clauses come in many shapes and sizes, ranging from the simple clause providing for cancellation/termination of the contract in the event that performance is prevented by circumstances comprehended within the term force majeure, to clauses of immense complexity containing, inter alia, a list of excusing events, provisions for notices to be issued to the promisee and detailing the consequences of the force majeure event
Show Solution

The Correct Option is C

Solution and Explanation

Contract frustration and force majeure are separate legal ideas. Both deal with the inability to fulfill a contract, but frustration arises automatically under the law, while force majeure is based on the contract's terms.
The correct answer is (C): ‘Frustration of contract’ and ‘force majeure’ are incorrectly presented as identical.

Was this answer helpful?
0
Question: 2

Which of the following is a leading judgement on ‘frustration of contract’?

Updated On: Jan 13, 2026
  • Central Inland Water Transport Corporation v. Brojo Nath Ganguly, (1986) 3 SCC 156
  • Satyabrata Ghose v. Mugneeram Bangur & Co., 1954 SCR 310.
  • Fateh Chand v. Balkishan Dass, (1964) 1 SCR 515
  • Thornton v. Shoe Lane Parking Ltd., (1971) 2 QB 163 (CA).
Show Solution

The Correct Option is B

Solution and Explanation

The case of Satyabrata Ghose v. Mugneeram Bangur Co. is a key ruling in Indian law regarding the legal principle of frustration, which deals with contracts becoming impossible to fulfill. The accurate answer is (B): Satyabrata Ghose v. Mugneeram Bangur & Co., 1954 SCR 310.

Was this answer helpful?
0
Question: 3

Which of the following is an incorrect proposition as regards frustration of contract?

Updated On: Jan 13, 2026
  • The courts have the general power to absolve a party from the performance of its part of the contract if its performance has become onerous on account of an unforeseen turn of event
  • If a contract contains a term according to which it would stand discharged on the happening of certain contingencies, dissolution of the contract would take place under the terms of the contract itself and such cases would be outside the purview of section 56 of the Indian Contract Act; such cases have to be dealt with under section 32 of the Indian Contract Ac
  • The application of the doctrine of frustration must always be within narrow limits
  • Section 56 of the Indian Contract Act does not apply to lease (completed conveyance
Show Solution

The Correct Option is A

Solution and Explanation

Courts generally cannot excuse a party from fulfilling a contract simply because it's become difficult; contract frustration demands impossibility or illegality.
The correct choice is (A): Courts can generally release a party from its contractual obligations if unforeseen events make performance excessively burdensome.

Was this answer helpful?
0
Question: 4

In Energy Watchdog v. Central Electricity Regulatory Commission, the Supreme Court found that the fundamental basis of the power purchase agreements (PPAs) between the parties was not premised on the price of coal imported from Indonesia. In fact, in the PPAs, there was a clause providing that changes in the cost of fuel, or the agreement becoming onerous to perform, are not treated as force majeure. Therefore, on the ground of the rise in price of Indonesian coal, the Court held that:

Updated On: Jan 13, 2026
  • Alternative modes of performance were available, albeit at a higher price; and that alone could not lead to the contract, as a whole, being frustrated.
  • The contract was frustrated on account of an unexpected rise in the price of Indonesian coal excusing the generating company from performing its part of the contract
  • The contract was frustrated on account of an unexpected rise in the price of Indonesian coal excusing the generating company from performing its part of the contract
  • The contract was frustrated on account of an unexpected rise in the price of Indonesian coal because the performance of an act might not be literally impossible, but it may be impracticable and useless from the point of view of the object and purpose of the contract.
Show Solution

The Correct Option is A

Solution and Explanation

According to the Energy Watchdog ruling, a contract isn't frustrated just because costs rise, because fulfilling the contract at a higher cost remains possible.
The right answer is (A): The contract could still be carried out in different ways, even if it cost more, which meant the entire contract wasn't frustrated.

Was this answer helpful?
0
Question: 5

The maxim lex non cogit ad impossibilia means:

Updated On: Jan 13, 2026
  • A personal right of action dies with the person
  • The burden of proof lies upon him who asserts and not upon him who denies
  • No person can claim any right arising out of his own wrongdoing.
  • The law does not compel a promisor to do that which is impossible to perform.
Show Solution

The Correct Option is D

Solution and Explanation

The principle of *lex non cogit ad impossibilia* means "the law doesn't force someone to do what's impossible," highlighting that the law won't demand the fulfillment of impossible duties.
The correct answer is (D): The law does not compel a promisor to do that which is impossible to perform.

Was this answer helpful?
0

Top Questions on Contract Law


Questions Asked in CLAT PG exam