Question:medium

In work-study (time and motion study) applied to mining operations, what is the primary purpose of a “rating factor”?

Show Hint

In work measurement, \[ \boxed{ \text{Normal Time} = \text{Observed Time} \times \text{Performance Rating}. } \] Standard Time is obtained after adding allowances.
Updated On: Jul 14, 2026
  • To adjust the observed time to standard time based on worker's performance level
  • To calculate machine availability
  • To determine labour cost per ton
  • To measure drill penetration rate
Show Solution

The Correct Option is A