Question:medium

In project management, the "Critical Path" in a PERT/CPM chart represents:

Show Hint

On a Critical Path, the Total Float is always Zero. This path determines the absolute minimum time required to complete the project.
Updated On: Jul 4, 2026
  • The shortest sequence of tasks in the project.
  • The path with the maximum slack/float.
  • The longest path of planned activities to the end of the project.
  • The path containing only non-essential tasks.
Show Solution

The Correct Option is C

Solution and Explanation