Question:medium

In a project network, two parallel activities start from the same node and merge at the same succeeding node. Their durations are: Activity A = 6 days, Activity B = 9 days. Which statement is correct?

Show Hint

For parallel activities sharing the same start and end nodes, the activity with the maximum duration acts as the bottleneck and will always lie on the critical path.
Updated On: Jul 9, 2026
  • Both activities lie on the critical path
  • Only Activity A lies on the critical path
  • Only Activity B lies on the critical path
  • Neither activity lies on the critical path
Show Solution

The Correct Option is C

Solution and Explanation