In a project network, two parallel activities start from the same node and merge at the same succeeding node. Their durations are: Activity A = 6 days, Activity B = 9 days. Which statement is correct?
Show Hint
For parallel activities sharing the same start and end nodes, the activity with the maximum duration acts as the bottleneck and will always lie on the critical path.