If two projects have the same PVB but Project A has a higher IRR than Project B, what is the usual recommendation when capital is limited?

Show Hint

For capital-constrained projects, \[ \boxed{ \text{Higher IRR} \Rightarrow \text{Higher return per unit investment}. } \]
Updated On: Jul 14, 2026
  • Choose the project with the higher NPV regardless of IRR
  • Choose the project with the higher IRR
  • Always choose the project with a longer life
  • Reject both projects
Show Solution

The Correct Option is B

Solution and Explanation

Was this answer helpful?