Question:medium

Gantt charts

Show Hint

Gantt Chart Layout: - Tasks are listed down vertically. - Time flows across horizontally. - Therefore, progress bars run horizontally! It is a quick visual tool to see exactly "what" needs to happen and "when" across a project timeline.
Updated On: Jun 23, 2026
  • Are vertical bar-based charts used for scheduling and tracking projects
  • Are horizontal bar-based charts used for scheduling and tracking projects
  • Focus on workflow logic and complex tasks
  • Provide overviews on goals and outcomes
Show Solution

The Correct Option is B

Solution and Explanation