Less than or equal to earliest event of the following node
Greater than or equal to earliest event of the following node
Show Solution
The Correct Option isC
Solution and Explanation
Step 1: Earliest Finish Definition.
The earliest finish time of a task is the earliest possible completion time, considering its dependencies. This time must be no later than the earliest start time of the subsequent node.
Step 2: Answer.
Therefore, the correct answer is (3): the earliest finish is less than or equal to the earliest event of the following node.
Final Answer:
\[
\boxed{3. \, \text{Less than or equal to the earliest event of the following node.}}
\]