Question:medium

Earliest finish of an activity is always:

Show Hint

In project scheduling, the earliest finish is always less than or equal to the earliest event of the succeeding node.
Updated On: Feb 18, 2026
  • Less than earliest event of the following node
  • Greater than earliest event of the following node
  • Less than or equal to earliest event of the following node
  • Greater than or equal to earliest event of the following node
Show Solution

The Correct Option is C

Solution and Explanation

Step 1: Earliest Finish Definition.
The earliest finish time of a task is the earliest possible completion time, considering its dependencies. This time must be no later than the earliest start time of the subsequent node.

Step 2: Answer.
Therefore, the correct answer is (3): the earliest finish is less than or equal to the earliest event of the following node.

Final Answer:
\[ \boxed{3. \, \text{Less than or equal to the earliest event of the following node.}} \]