Cylindrical workpieces of diameter 60 mm and length 400 mm are machined on a lathe at a cutting speed of 25 m/min and a feed of 0.2 mm/rev. The Taylor’s tool life parameters \(C\) and \(n\) for this setup are 75 and 0.25, respectively. The tool changing time is 3 minutes. With a labor and overhead cost of ₹5 per minute, the tool changing cost per piece is ₹_________ (rounded off to 2 decimal places).
A project involves eight activities with the precedence relationship and duration as shown in the table below. The slack for the activity D ____________ hours (answer in integer).
A company uses 3000 units of a part annually. The units are priced as given in the table below. It costs rupee 150 to place an order. Carrying costs are 40 percent of the purchase price per unit on an annual basis. The minimum total annual cost is rupee ___________ (rounded off to 1 decimal place).} 