Step 1: Assessing Instrumentation Expenses.
In contemporary chemical facilities, instrumentation expenses constitute a minor fraction of the overall project expenditure, typically falling between 1.5% and 10% of the total investment.
Step 2: Evaluating Alternatives.
- (A) The standard range for instrumentation costs is 1.5% to 10%. - (B), (C), and (D) These figures represent excessive costs for instrumentation, as they surpass the typical 10% threshold in standard plant configurations.
Conclusion: \[\boxed{\text{A) 1.5 to 10%}}\]